The Hospital AI Assistant project builds an AI system that reads uploaded documents, extracts tasks and deadlines, and auto-generates executive reports for hospital staff. Budget is $120,000; runtime is July–October 2026; success is defined as a 60% reduction in manual reporting time.
Foundational work (UI, database) is complete. The critical path — API integration, authentication, testing — is in progress or pending, and carries the project's real schedule risk. Two client-driven commitments (Arabic/English support, Aug 5 dashboard) add near-term delivery pressure on top of the internal build schedule.
| Milestone | Date | Source |
|---|---|---|
| UI complete | Jul 15 | Tracker |
| Database complete | Jul 16 | Tracker |
| API development complete | Jul 18 | Tracker / Minutes |
| Authentication complete | Jul 19 | Tracker |
| Testing complete | Jul 20 | Tracker / Minutes |
| Deployment | Jul 28 | Tracker |
| Documentation complete | Jul 30 | Tracker |
| Client dashboard delivery | Aug 5 | Minutes only |
| Owner | Task | Priority | Deadline |
|---|---|---|---|
| Sara | UI Design | High | Jul 15 |
| Ahmed | API Development | High | Jul 18 |
| Ali | Database | Medium | Jul 16 |
| Noor | Authentication | High | Jul 19 |
| Mona | Testing | High | Jul 20 |
| Omar | Deployment | Medium | Jul 28 |
| Lina | Documentation | Low | Jul 30 |
Role titles (Project Manager, AI Engineer, Backend Developer, QA Lead) appear only in Meeting Minutes; a name-to-role mapping is not found in the uploaded documents.
2 of 7 tasks complete · 1 in progress · 4 pending/not started
| Task | Status |
|---|---|
| UI Design | Completed |
| Database | Completed |
| API Development | In Progress |
| Authentication | Pending |
| Testing | Pending |
| Deployment | Pending |
| Documentation | Not Started |